S1 DB -4
R1 - 32 done
Y2 - 43 M. Done
Y3 - 19 m done
R4 - 31 m done
B5 53 done
Y6 - 66 done
B7 - 51 done
Y9 - 100 M Done
B8 - 99 M Done
Y10 - 79. Done
R 11 75 M done
Total 648 M
S1 BD-2
R5 - 15M ok
R8- 43M ok
R9 - 50M ok
B7 52M ok
B6 36M ok
B2 71M ok
R3 79M ok
B4 86M ok
B1 95 M ok
Total 527 M
S1 DB -3
Y2 - 13 m ok
Y4 - 50 m ok
Y3 - 53m ok
R1 - 75m ok
Looping DB Arif Sir
📌S3
Arif Sir achinta kaku
S3 looping
16m
14m
35m
13m
40m
📌Looping Db - 2
Y 5 - 15 m
📌DB - 3
R2-y2 - 34m ok
R5 - y5 -15 m ok
R3 - B3 - 31m ok
📌DB - 4
R1 - Y1 - 38 m
R2 - Y2 - 22m
Y1 - B1 - 33m
Y2 - B2 - 17m
Y3 - R3 - B3 25 m
R4 - Y4 L B4 20m
Y6 -13m
R7 - 25 m
B2 Z3 FM EA
169
170
171 (6) 2 pic
Complete
B2 Z2 JET F3
DB 3 right side
185+4 =189
186+4 =190
187+4 = 191 ( 6) 2 pic
Complite
B2 Z4 Fm Ea
158
159
161 (6) 2 pic
Complete
B1 Z5 6 core 2.5 sq
1done
2 done
3 done
Z5 5no - 48m
Z5 4 no - 30 m
Z5 6no - 43 m
Z5 7no - 62 m
Complete
Tower 2 3c 4 sq
No 1 - 62 m
No 2 121m
Star case light post 79
262m
Tower 3 taris 3 core 4 sq
1. 51m UPS DB BOX. HRW1 OK
2 52 m . ok
3 .14m looping no2 to no 3. ok
4 74m . Taris HRW2 ok
5 looping 11 m taris
6. 15 m
Total 202
Complete
B2 Exl Fan 3 core 4 sq
Zone 1
155 no - 1
155 no - 1-2
153 mid no -2
155 no - 3
Total = 618m
Complete done
B1 new 4 core 25 sq
DB-2 -B1/P2 -65M
BD 2 - B1/P2- 65M
S1 3 core 6
Big fan 1 82m 2 run 3 x6
Fan 3 -69 3core left
Fan1- 65
Fan2 -68 right
Big fan 2 - 13 M 2 run 3x6
TOTAL 392
S3 3.5 core 50 sq
Db 3 - 127m
DB 1- 47m
Complete
B2 cable 50mm new
Car Chargeing
MAIN DB TO DB 2 - 50M done
MAIN DB TO DB 3 - 44M 95sq done
MAIN DB TO DB 4 - 90m done
B2 Zet Fan New 6 core 2.5 cable
Z2 - 03- 30 m ok
Z2 - 04 -43 m ok
Z2 - 02 - 57m ok
Z2 -01 - 87m
Z2- 06 - 118 m
Z2 - 07 - 114 m
Z2 - 05 - 70m
Z2 - 10 - 144m
Z2 - 09 - 127m
Z2 08 - 99m
Total= 889m
Z1- 01 - 87m
Z1 - 02- 59m
Z1 - 03 - 29m
Z1- 04 - 44m
Z1 - 05 - 78 m
Z1 - 06 - 96m
Z1 - 07 - 109m
Z1 - 08 - 122 m
Z1 - 09 - 146m
Total - 758 m
Z3 - 01 already
Z2 - 02 already
Z3 - 03 already
Z3- 04 58m
Z3-05 already
Z3- 06 - 68m
Z3 - 07 - 99m
Z3 - 08 - 120m
Total= 345m
Z4 - 06 - 104m
Z4 - 05 - 47m
Total= 151m
Z5 - 06- Confusion
Z5 - 07 -58m
Total=58
Z6 - 03 - 62 M
Z6- 01 - 62 M
Z6 02- 36M
B1 Exl Fan
98m
99m
B2 New magerment 4 core 1.5 Zet Fan
Z1 - 4 no - 28 m. Done
Z1 - 5 no - 60m done
Z1 - 6 no - 87m. Done
Z1 - 7 no - 126m done
Z1 - 8 no -125m. Done
Z1 - 9 no -140m. Done
Z2 - 11 no- 165 m right. Done
Z2 - 10 no - 143 m right. Done
Z2 - 9 no - 131 m. done
Z2 - 8 no - 118m. Done
Z2 - 7 no - 123m ok done
Z2 - 6 no -84 m right done
Z2 - 5 no - already Completed .
Z2 - 4 no -22m right done
Total - 1352m
S3
111
129
137m final
S3 HVAC panel 2- 14m final